eLanka

Monday, 22 Sep 2025
  • Home
  • Read History
  • Articles
    • eLanka Journalists
  • Events
  • Useful links
    • Obituaries
    • Seeking to Contact
    • eLanka Newsletters
    • eLanka Testimonials
    • Sri Lanka Newspapers
    • Sri Lanka TV LIVE
    • Sri Lanka Radio
    • eLanka Recepies
  • Gallery
  • Contact
Newsletter
  • eLanka Weddings
  • Property
  • eLanka Shop
  • Business Directory
eLankaeLanka
Font ResizerAa
Search
  • Home
  • Read History
  • Articles
    • eLanka Journalists
  • Events
  • Useful links
    • Obituaries
    • Seeking to Contact
    • eLanka Newsletters
    • eLanka Testimonials
    • Sri Lanka Newspapers
    • Sri Lanka TV LIVE
    • Sri Lanka Radio
    • eLanka Recepies
  • Gallery
  • Contact
Follow US
© 2005 – 2025 eLanka Pty Ltd. All Rights Reserved.
Home » Blog » Articles » Athweltota mini hydro project Sensitive ecosystems threatened as renewable energy projects emerge-By Kamanthi Wickramasinghe
Articles

Athweltota mini hydro project Sensitive ecosystems threatened as renewable energy projects emerge-By Kamanthi Wickramasinghe

eLanka admin
Last updated: January 19, 2022 5:02 pm
By
eLanka admin
ByeLanka admin
Follow:
Share
12 Min Read
SHARE

Athweltota mini hydro project Sensitive ecosystems threatened as renewable energy projects emerge-By Kamanthi Wickramasinghe

Serene Pilithuda Falls in Athweltota

 Serene Pilithuda Falls in Athweltota

Source:Dailymirror

  • There are 213 commissioned mini hydro projects and 40 solar power plants in Sri Lanka and the numbers continue to increase    
  • Many of these projects don’t operate efficiently and therefore the contribution to the national grid is limited  
  • The Palindanuwara Provincial Council has repeatedly questioned how a mini hydro project could be constructed in a high risk area  
  • Many solar power plants are constructed by clearing forests  
  • Elephant corridors and sensitive ecosystems are destroyed in the process of making power plants in the absence of a plan to conserve catchment areas  
  • The CEB and SLSEA should improve the efficiency in existing plants before constructing new plants  

Sri Lanka aims to be an energy self-sufficient nation by 2030. Right now, the primary sources of generating electricity include thermal, including coal and fossil fuels, hydropower and other non-conventional renewable energy sources such as solar and wind. However, the renewable energy sector has transformed itself into a money-spinning industry with the emergence of solar plants and mini hydro projects scattered across the country. So far, there are 213 commissioned mini hydro projects and 40 solar power plants in Sri Lanka and the numbers continue to increase. However, many of these projects don’t operate efficiently and therefore the contribution to the national grid is limited. Apart from that many projects are being constructed in highly sensitive ecosystems or landslide-prone areas, posing greater threats to wildlife as well as people in surrounding areas. 

More Read

The Bangkok Gems & Jewellery Fair – By Dr Harold Gunatillake
Anula Vidyalaya Alumni NSW & ACT Presents – Aradhana 2025
Sydney Expatriates Meet Dr. Harsha de Silva, MP and the Chairman of the Finance Committee of Sri Lanka Parliament
MOVA Partners with FILMBASE to Bring Next-Generation Smart Glass & LED Film Solutions to Sri Lanka

Serene Pilithuda Falls in Athweltota 2

Serene environment under threat   

Peelithuda Falls is a tributary (a river or stream flowing into a larger river or lake) in the Sinharaja ecosystem, located near Pelan River at Athweltota, Morapitiya in the Palindanuwara Divisional Secretariat. “The ecosystem associated with this waterfall is a region of high biodiversity and is home to over 32 endemic freshwater fishes,” opined Senior Consultant at Centre for Environmental Justice, Hemantha Withanage. “However, in 2007 a proposal to construct a 1.5 megawatt (MW) mini hydro power plant, by Sakura Energy Ltd., comes to light. According to the plan a 1.5 metre embankment will be built and about 900 metres of the river will be drained to generate electricity. As a result, a lot of trees need to be felled for this purpose, disrupting the entire ecosystem,” said Withanage.   

More Read

Sri Lanka hosts the Asia Pacific Motorsport Championship 2025! 01
Sri Lanka hosts the Asia Pacific Motorsport Championship 2025!
eLanka Newsletter -21st September 2025 – 3rd Edition – Sri Lankans In Australia
Foods that can naturally support better sleep
Fabulous Sri Lankan fare and great music makes the Springvale RSL the place to be. By Trevine Rodrigo in Melbourne.

Villagers utilise this river during the dry season and it is a tourist attraction as well. “Out of the 32 endemic freshwater fishes found here, 15 of them are confined to this area. Among them, species such as Rasboroides nigromaginatus (Kalu waral halmal dandiya), Stiphodon martenstyni are critically threatened. Some of the vulnerable species include Garra ceylonensis (Gal paadiya) and Channa orientalis (Kola kanaya). Apart from that, this area is a landslide-prone area and as a result of a landslide that occurred in 2017, nine lives were lost. The powerhouse for this project will be built near a landslide-prone area. Even though the National Building Research Organisation (NBRO) has issued red notices for people to evacuate to safer locations, they have issued recommendations to continue this project.   


“ The concurrence was done in 2014 and the documents are now at the legal department”-
Siripala Amarasinghe CEA Chairman

Legal procedures bypassed?

In 2017 the Centre for Environmental Justice (CEJ) had filed a case to request for a Strategic Environmental Assessment (SEA), prior to constructing mini hydro projects. “Parties including the Ceylon Electricity Board, Central Environmental Authority, Ministry of Environment and Sustainable Energy Authority collectively agreed to formulate a SEA prior to giving approval for mini hydro projects. Most mini hydro power plants cause irreversible damage to the environment. Many dump their e-waste into rivers and as a result, rivers get clogged. As a result of this discussion, they agreed to investigate and earmark designated areas along rivers which could be given for the construction of such projects and which areas need to be protected. But before the incumbent government came into power this agreement was dismissed and we had to withdraw the case. Had we come into an agreement to conduct SEAs, the designated rivers could have been earmarked,” he said.   

More Read

Watch Asia Cup 2025 (T20) Sri Lanka Cricket Match Highlights
Penetrating Sri Lanka: Foreign Enclaves & Global Powers-by Dr Asoka Bandarage
A Ripping & Gripping Cricketing Fight: Lanka vs Afghanistan-by Michael Roberts
The Brad and Kiara Show Sept 20

Protest staged by area residents urging authorities to halt the proposed mini hydro project   

He further said that the Palindanuwara Provincial Council has repeatedly questioned how a mini hydro project could be constructed in a high risk area. “Members of the Council have not only disapproved this project, but have also sent a letter to the Minister of Energy, reasoning out why this project shouldn’t be carried out at this location. But it is in such a backdrop that the contractors are once again starting to do site inspections to proceed with the project,” Withanage further reasoned.  

Apart from that though the Initial Environmental Examination (IEE) was done in 2014 this document is now invalid. Section 23B of the National Environmental Act No. 47 of 1980 states that the validity of such a document is only for three years. Thereafter, any permit or validity given to a project expires and requires a renewal.   


 

 “Most mini hydro power plants cause irreversible damage to the environment. Many dump their e-waste into rivers and as a result, rivers get clogged. As a result of this discussion, they agreed to investigate and earmark designated areas along rivers which could be given for the construction of such projects”- Hemantha Withanage Senior Consultant at Centre for Environmental Justice

Impact on aquatic ecosystems   

In his comments, Environmentalist Sajeewa Chamikara said that renewable power plants in Sri Lanka don’t operate in an efficient manner. “They still use archaic technologies and therefore we cannot produce a maximum capacity. On the other hand there’s no plan to conserve catchment areas of major reservoirs such as Victoria, Randenigala and Rantambe. But they continue to generate electricity, thereby leading to a water crisis. Many solar power plants are constructed by clearing forests. Elephant corridors and sensitive ecosystems are destroyed this way.  

“Therefore the CEB and SLSEA should improve the efficiency in existing plants before constructing new plants. People need to be made aware of utilising these resources in an efficient manner. This has resulted in a major power crisis and as a solution, solar power plants and mini hydro plants are constructed in inappropriate locations,” Chamikara added.  

He further shed light on how disrupting the flow of water in rivers could impact freshwater fishes and endemic aquatic plants such as Ketala and Kekatiya. “Some freshwater fish need to reach the estuary or marine environment for breeding. For example eels lay eggs in marine environments. They come down towards the lagoon, change their body colour, reach their breeding sites. The young then follow their parents back to freshwater systems. When dams are constructed across rivers, their life cycles are disrupted. Most freshwater fish lay eggs at the beginning of the monsoon season. With the rains, these eggs flow down towards the lagoon and eventually hatch. But the authorities have no clue about the sensitivity of these ecosystems,” he added while emphasising that the environment at Pilithuda Falls would have drastically changed over a period of six years and that constructing a mini hydro power plant would pose greater threats to the environment.  

Less impacts from the project : NBRO

In his comments, Dr. H. A. G. Jayatissa serving at NBRO’s Landslide Risk Research Management Division said that landslides could be activated due to anthropogenic activities. “We need to promote green energy and when we have a project of this nature we will assess if there are negative impacts from the project. Since a dam is being built the water levels won’t rise. But there’s a tendency for the soil to loosen and without a tow support, the lower area will wash away. This is a project-induced threat. As such we will assess such threats and provide recommendations to carry out the project in a sustainable manner.” said Jayatissa.   

When asked if the relevant project-approving authorities would monitor if the contractor is complying to the recommendations, he said that all authorities including CEA, forest conservation department and NBRO would jointly monitor if the contractor is adhering to the recommendations. “If these are not being implemented we will stop the project.” added Jayatissa.   

He further said that the impact of the project is less and that’s why the NBRO has given the clearance. “Almost all (95%) mini hydro projects are in landslide-prone areas. We can’t stop such projects as we promote green energy, but we give recommendations to minimise landslide impacts that will happen from such a project,” he added.  
No approval given yet : Forest Conservation Department 

However, Deputy Forest Conservator Nishantha Edirisinghe said that the project hasn’t been approved as yet since there are several issues to be rectified first.  


“They still use archaic technologies and therefore we cannot produce a maximum capacity. On the other hand there’s no plan to conserve catchment areas of major reservoirs such as Victoria, Randenigala and Rantambe”- 

Sajeewa Chamikara Environmentalist

Documents at the legal department : CEA  

When contacted CEA Chairman Siripala Amarasinghe said “The concurrence was done in 2014 and the documents are now at the legal department,”. Speaking further he added, “We therefore have to decide whether another concurrence is needed before giving clearance to the project.”.   

Repeated attempts to contact SLSEA Chairman Ranjith Sepala and State Minister of Solar, Wind and Hydro Power Generation Projects Development Duminda Dissanayake proved futile. A senior official at Sakura Energy (Pvt) Ltd., declined to comment on the matter.   

TAGGED:Duminda DissanayakeNishantha EdirisingheSerene Pilithuda FallsSiripala Amarasinghe
Share This Article
Email Copy Link Print
Previous Article SBS Sinhala discussion with the Sri Lankan from SA who was awarded by Australia for his dedication of twenty plus years of community services SBS Sinhala discussion with the Sri Lankan from SA who was awarded by Australia for his dedication of twenty plus years of community services
Next Article The Telephone The Telephone
FacebookLike
YoutubeSubscribe
LinkedInFollow
Most Read
10 Pictures With Fascinating Stories Behind Them!

“A PICTURE SPEAKS A 1000 WORDS” – By Des Kelly

Look past your thoughts so you may drink the pure nectar of this moment

A Life Hack for when we’re Burnt Out & Broken Down – By Uma Panch

Narration of the History of our Proud Ancestral (Orang Jawa) Heritage. by Noor R. Rahim

eLanka Weddings

eLanka Marriage Proposals

Noel News

Noel News

Noel News

Noel News- By Noel Whittaker

EILEEN MARY SIBELLE DE SILVA (nee DISSANAYAKE) – 29 September 1922 – 6 April 2018 – A Woman of Value an Appreciation written by Mohini Gunasekera

K.K.S. Cement Factory

Dr.Harold Gunatillake’s 90th Birthday party

Sri Lanka's women's cricket squad in Melbourne

Cricket: Sri Lanka’s women’s squad in Melbourne

- Advertisement -
Ad image
Related News
Articles

Zahira College’s 11th Colombo Scout Group Unites Over 700 Scouts at Jamboree 2025 Celebrating 110 Years of Scouting Excellence

Cultural Reflections
Articles Bhanuka Nuwan

Cultural Reflections: Relics, Rituals, and the Meditation on a Passing Era – by Bhanuka – eLanka

Balancing Growth and Burdens The Economic Challenges Ahead for Sri Lanka - By Nadeeka - eLanka (1)
Articles Nadeeka Kumari

Balancing Growth and Burdens: The Economic Challenges Ahead for Sri Lanka – By Nadeeka – eLanka

SUNDAY CHOICE - Jesus, keep me near the Cross -A message for Lent - By Charles Schokman - eLanka
Articles Charles Schokman

SUNDAY CHOICE – Yet not I, but through Christ in me – by Charles Schokman

World-Class Creative Writing in Sri Lanka-eLanka
Articles

Pursuing World-Class Creative Writing in Sri Lanka-by Dr Sasanka Perera

  • Quick Links:
  • Articles
  • DESMOND KELLY
  • Dr Harold Gunatillake
  • English Videos
  • Sri Lanka
  • Sinhala Videos
  • eLanka Newsletters
  • Obituaries
  • Tamil Videos
  • Dr. Harold Gunatillake
  • Sunil Thenabadu
  • Sinhala Movies
  • Trevine Rodrigo
  • Michael Roberts
  • Photos

eLanka

Your Trusted Source for News & Community Stories: Stay connected with reliable updates, inspiring features, and breaking news. From politics and technology to culture, lifestyle, and events, eLanka brings you stories that matter — keeping you informed, engaged, and connected 24/7.
Kerrie road, Oatlands , NSW 2117 , Australia.
Email : info@eLanka.com.au / rasangivjes@gmail.com.
WhatsApp : +61402905275 / +94775882546

(c) 2005 – 2025 eLanka Pty Ltd. All Rights Reserved.